Code Section

Health and Safety Code - HSC

DIVISION 20. MISCELLANEOUS HEALTH AND SAFETY PROVISIONS [24000 - 26275]

  ( Division 20 enacted by Stats. 1939, Ch. 60. )
  

CHAPTER 6.7. Underground Storage of Hazardous Substances [25280 - 25299.8]
  ( Chapter 6.7 added by Stats. 1983, Ch. 1046, Sec. 3. )

  
25288.  

(a)  The local agency shall inspect every underground tank system within its jurisdiction at least once every year. The purpose of the inspection is to determine whether the tank system complies with the applicable requirements of this chapter and the regulations adopted by the board pursuant to Section 25299.3, including the design and construction standards of Section 25290.1, 25290.2, 25291, or 25292, whichever is applicable, whether the owner or operator has monitored and tested the tank system as required by the permit, and whether the tank system is in a safe operating condition.

(b)  After an inspection conducted pursuant to subdivision (a), the local agency shall prepare a compliance report detailing the inspection and shall send a copy of this report to the permitholder and the owner or operator, if the owner or operator is not the permitholder. Any report prepared pursuant to this section shall be consolidated into any other inspection reports required pursuant to Chapter 6.11 (commencing with Section 25404), the requirements listed in subdivision (c) of Section 25404, and the regulations adopted to implement the requirements listed in subdivision (c) of Section 25404.

(c)  In lieu of the annual local agency inspections, the local agency may require the permitholder to employ a special inspector to conduct the annual inspection. The local agency shall supply the permitholder with a list of at least three special inspectors that are qualified to conduct the inspection. The permitholder shall employ a special inspector from the list provided by the local agency. The special inspector’s authority shall be the same as that of the local agency as set forth in subdivision (a).

(d)  Within 60 days after receiving a compliance report or special inspection report prepared in accordance with subdivision (b) or (c), respectively, the permitholder shall file with the local agency a plan to implement all recommendations contained in the compliance report or shall demonstrate, to the satisfaction of the local agency, why these recommendations should not be implemented. Any corrective action conducted pursuant to the recommendations in the report shall be taken pursuant to Sections 25296.10 and 25299.36.

(Amended by Stats. 2003, Ch. 42, Sec. 5. Effective July 7, 2003.)