All improvements are subject to inspection by the City. The City shall, upon not less than one working day’s advance notice or request, make such inspections as are requested and as is deemed necessary to ensure that all construction is in accordance with the approved plans and specifications and in no case shall such inspection be less than:

A. The inspection of all underground utility, gas, electric, telephone, water, sewer, drainage and fire service lines.

B. An inspection of the subgrade prior to placing the rock base.

C. An inspection of road base prior to placing of roadway surfacing.

D. An inspection of paving.

E. The inspection of concrete forms.

F. The inspection of the pouring of any concrete.

G. A final inspection of the grading.

H. An inspection of street lights.

I. Inspections by other City departments as required.

J. A final inspection upon completion of all improvements for the subdivision.

The subdivider shall notify the City Engineer upon the completion of each stage identified above and shall not proceed until the subdivider has received the authorized approval.